The Alameda County Public Works Agency has several projects along Crow Canyon Road, between East Castro Valley Boulevard and the County line. These projects are being implemented in four phases and include roadway resurfacing, pavement reconstruction, storm damage repair, and various safety improvements.
Project Features
Phase I - Resurfacing and Safety Improvements
- Resurface pavement between East Castro Valley Blvd and Cold Water Drive
- Construct roadway shoulder improvements to accommodate traffic law enforcement
- Install pedestrian ramps, speed feedback signs, and new guardrails
- Replace damaged culverts under roadway
- Install traffic signal improvements
- Install retaining walls between MM 6.00 and MM 6.25
- Perform roadway pavement reconstruction from MM 5.25 to the County line
- Replace/Install guardrails
- Install centerline rumble strips
- Culvert replacement
- Signing and striping
Phase IV – Guardrail Replacement
- Replace existing guardrails from San Simeon place to Norris Canyon Road
Community Outreach
CIP Category
Pavement Rehabilitation and Transportation Infrastructure Safety
Construction Start Date
Phase I Resurfacing and Safety Improvements - December 2021
Phase II Storm Damage Repair - September 2022
Phase III Pavement Reconstruction - Summer 2024
Phase IV Guardrail Replacement – Summer 2024
Status
- (All) Projects Completed (i.e Phases I thru IV)
Project Location
Crow Canyon Road, from East Castro Valley Blvd. to the Contra Costa/Alameda County Line
District
District 4
Project Manager
Bond Ng, Associate Civil Engineer
James Lai, Supervising Construction Inspector
Contact
For more information email info@acpwa.org or call the construction hotline at (510) 670-5591. Click here to receive e-mail updates.