Project Overview
The Proctor Road Sidewalk Improvement Project is located in Castro Valley, along Proctor Road from Walnut Road to Camino Alta Mira. The project will provide infill and replacement sidewalks on both sides of Proctor Road, along with curb ramp upgrades at intersections within the project limits. The goal is to establish a continuous ADA-compliant path of travel on both sides of the roadway. Traffic control measures and best management practices (BMPs) will be implemented to protect the environment, and utility relocations will also be included.
Construction is planned in two phases. Phase 1 will be Proctor Road East, which is on Proctor Road east of Redwood Road to Camino Alta Mira. Phase 2 will be Proctor Road West, which is west of Redwood Road to Walnut Road.
Project Features
- New Sidewalks
- New Concrete Curbs and Gutters
- New Curb Ramps
- New Driveways
- Landscaping and Street Trees
- Pavement Maintenance
Community Meeting
A virtual public meeting was held on Tuesday, January 28, 2025 , where the design for both phases of the Proctor Road Sidewalk Improvement Project was presented. This meeting offered a valuable opportunity for community members to learn more about these projects.
Recording: Proctor Meeting Zoom
CIP Category
Sidewalk Improvement Program
Construction Start Date
Proctor Road East: August 2025
Proctor Road West: Spring 2026
Status
Proctor Road East: This project is currently under construction
Proctor Road West: Design
Project Location
Phase 1: Proctor Road, between Redwood Road and Camino Alta Mira
Phase 2: Proctor Road, between Walnut Road and Redwood Road
Supervisorial District
District 4
Project Manager
Emanual Kasegne
LaVonne Scott, Construction Inspector
Contact
For more information email info@acpwa.org or call the construction hotline at (510) 670-5437