Mission Creek Crossing Improvements

Project Overview

The Mission Creek Crossing Improvement Project at Lemos Lane will improve flood protection to the adjacent community by increasing culvert conveyance capacity. The project will be completed in two phases. Phase 1 involves the relocation of a water line. Phase 2 will involve the construction of two additional 12’ wide by 8’ high box culverts.

Project Features

  • Two 12’ wide by 8’ high concrete box culverts under Lemos Lane

Public Notice from May 19, 2023 

CIP Category

Capacity Improvement Project

Construction Start Date

Phase 1 construction work was completed in August 2021.

Phase 2 construction was was completed in November 2023

Status

Construction has been completed.

Project Location

800 Block of Lemos Lane in Fremont



District

District 1

Project Manager

Moses Tsang

Contact

For more information email info@acpwa.org or call (510) 670-6549.  Click here to receive e-mail updates.