Mission Creek Crossing Improvements
Project Overview
The Mission Creek Crossing Improvement Project at Lemos Lane will improve flood protection to the adjacent community by increasing culvert conveyance capacity. The project will be completed in two phases. Phase 1 involves the relocation of a water line. Phase 2 will involve the construction of two additional 12’ wide by 8’ high box culverts.
Project Features
- Two 12’ wide by 8’ high concrete box culverts under Lemos Lane
CIP Category
Capacity Improvement Project
Construction Start Date
Phase 1 construction work was completed in August 2021.
Phase 2 construction was was completed in November 2023.
Status
Construction has been completed.
Project Location
800 Block of Lemos Lane in Fremont
Supervisorial District
District 1
Project Manager
Moses Tsang
Contact