San Lorenzo Creek - Line B

Concrete Channel Permanent Repair Downstream of Washington Ave

Project Overview

This project involves repairing the concrete channel bottom damaged by utility pipeline leaks. Work includes, but not limited to, removing and replacing the damaged portion of the reinforced concrete channel bottom, investigating the ruptured PG&E and EBMUD pipelines and performing all associated restoration work necessary to complete the repairs.

Project Features

  • Re-construction of reinforced concrete channel bottom

Community Outreach

Public Notice – June 8, 2026

 

CIP Category

Channel Stabilization

Construction Start Date

June 2026

Status

The project has been advertised for construction bids. The construction of this project is anticipated to start July 2026 and be completed by end of October 2026.

Project Location

Just downstream of Washington Avenue in the City of San Leandro

Hampton Road Map

Supervisorial District

District 3

Project Manager

Paul Knobel, P.E.

Yacob Ghebreyesus

Contact

Alameda County Public Work Agency’s Construction Department
Office Phone No.: (510) 670-5591; E-mail: info@acpwa.org , Click here to receive e-mail updates.